(一)、Ⅴ类加强段类围岩开挖与支护 施工顺序:超前管棚→侧壁导坑上部打眼→装药爆破→通风、找顶→初喷混凝土封闭岩面→出碴→测量→立拱架、挂钢筋网→施做系统锚杆→复喷至设计厚度→进入下一循环→(待超前2.5—3m后)→侧壁导坑下部打眼→装药爆破→通风、找顶→初喷混凝土封闭岩面→出碴→测量→立拱架、挂钢筋网→施做系统锚杆→复喷至设计厚度→进入下一循环
![](https://fd.co188.com/group1/M03/E1/41/rBBhH2KTKA2ABJ9iAACKupTUXd839.jpeg)
![](http://g.co188.com/img/topics/new_topics/images/blank.gif)
![](http://g.co188.com/img/topics/new_topics/images/blank.gif)
![](http://g.co188.com/img/topics/new_topics/images/blank.gif)
![](http://g.co188.com/img/topics/new_topics/images/blank.gif)
![](http://g.co188.com/img/topics/new_topics/images/blank.gif)
开挖支护方法
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
(一)、Ⅴ类加强段类围岩开挖与支护 施工顺序:超前管棚→侧壁导坑上部打眼→装药爆破→通风、找顶→初喷混凝土封闭岩面→出碴→测量→立拱架、挂钢筋网→施做系统锚杆→复喷至设计厚度→进入下一循环→(待超前2.5—3m后)→侧壁导坑下部打眼→装药爆破→通风、找顶→初喷混凝土封闭岩面→出碴→测量→立拱架、挂钢筋网→施做系统锚杆→复喷至设计厚度→进入下一循环
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
相关推荐